City of Nanaimo Construction Projects


Construction Season Now in Full Swing


Construction season in Nanaimo is underway. There are a number of City of Nanaimo projects already started, with more projects to start in the coming months. The following routes are currently affected:

• From May to September, water main and sewer replacements coinciding with the addition of a bike lane along Bruce Avenue from 5th to 7th Street. Temporary detours and single lane alternating traffic can be expected.

• From June to July, a new sidewalk will be installed on the southerly side of Hammond Bay Road between Tom's Turnabout and Dunn Place along with a new pedestrian activated warning flasher at the existing Hammond Bay Road crosswalk on the west side of Entwhistle Road. Following the sidewalk construction, this section of Hammond Bay Road will get repaved. Single lane alternating traffic can be expected.

• From May to August, water main replacement will affect Jingle Pot Road from Westwood Road to Harwell Road, Harwell Road from Jingle Pot Road to Woodthrush Place, and Westwood Road from Jingle Pot to Arbot Road. Single lane alternating traffic can be expected. To lessen the impacts for Westwood Lake Park users, work on Westwood Road will be completed in June.


allvoices

No comments:

Post a Comment

Your comment will appear after moderation before publishing,

Thank you for your comments.Any comment that could be considered slanderous or includes unacceptable language will be removed.

Thank you for participating and making your opinions known.

Note: only a member of this blog may post a comment.